News APP

NewsApp (Free)

Read news as it happens
Download NewsApp

Available on  gplay

This article was first published 12 years ago
Rediff.com  » Business » Toyota to pump in Rs 1,650 cr to hike capacity

Toyota to pump in Rs 1,650 cr to hike capacity

Source: PTI
July 27, 2011 13:00 IST
Get Rediff News in your Inbox:

ToyotaJapanese car giant Toyota on Wednesday announced an investment of nearly Rs 1,650 crore (Rs 16.5 billion) to ramp up the production capacity of its Indian operations by one lakh units and for increasing localisation of components by 2014.

The company, which is present in India through a joint venture with the Kirloskar Group, will invest Rs 898 crore (Rs 8.98 billion) to expand the production capacity of the two plants by 2013.

Another group firm will put in an additional Rs 750 crore (Rs 7.5 billion) to set up aluminum casting and machining lines by 2014.

"Toyota Kirloskar Motor on Wednesday announced a further increase of its production capacity to 3,10,000 units by 2013.

The expansion will come with an investment of Rs 898 crore approximately and generation of new employment opportunities," the company said.

The production capacity at the first plant will be enhanced from 90,000 units to 1,00,000 units, while the output at the second plant will be increased to 2,10,000 units from 1,20,000 units, it added.

TKM is at present expanding the capacity at the two facilities in Bangalore to 210,000 units from 150,000 units by 2012.

The first plant will manufacture multi-purpose vehicle Innova and sports utility vehicle Fortuner.

The second plant will roll out sedans Etios and Corolla Altis and hatchback Liva, the company said.

Commenting on development, TKM managing director Hiroshi Nakagawa said: "In line with the growing demand for our vehicles, we have decided to further expand production.

"The demand for Etios and

Etios Liva has been encouraging and we are gearing up to cater to a larger number of customers."

The company had last month launched the small car Liva and it has so far received booking orders for 4,000 units.

The sedan Etios was launched in December last year and received a good response from the market, forcing the company to expand its capacity earlier than planned.

TKM also said it will increase the localisation of components of the Etios and Liva, with Toyota Kirloskar Auto Parts Pvt Ltd planning to install and commission aluminum casting and machining lines by early 2014.

"The installation will see an additional investment of Rs 750 crore (Rs 7.5 billion) approximately and generation of new employment opportunities," it added.

The lines are to be installed at TKAP's new Etios and Liva engine plant, which is scheduled to start operations in the third quarter of 2012.

TKAP had earlier announced plans to set up an engine plant and expand its transmissions capacity to cater to demand for the Etios and Liva with a combined investment of Rs 500 crore (Rs 5 billion).

In addition, TKAP will start producing transmissions for the Etios and Liva in early 2013. Exports of the transmissions are also being planned, TKM said.

"TKAP serves as a production and supply base for manual transmission for IMV series vehicles to India, Thailand and Argentina," it added.

Commenting on the new project in India, TKM chairman Vikram Kirloskar said: "Etios and Etios Liva have been designed specifically for the Indian market.

"The localisation project is vital to provide best quality product at a competitive price."

Get Rediff News in your Inbox:
Source: PTI© Copyright 2024 PTI. All rights reserved. Republication or redistribution of PTI content, including by framing or similar means, is expressly prohibited without the prior written consent.
 

Moneywiz Live!